Updated Network upgrade schedule

Latest upgrade dates as of November 27, 2015  below.

The upgrade work being done on the University’s network has taken some expected twists and turns, and some not so expected.

As a result, the scheduled dates for each of the buildings and areas have been adjusted.

Below are the current (and somewhat still tentative) dates for the upcoming work:

  • University Hall – Substantially Complete
  • Centre for the Arts – Substantially Complete
  • LINC – Substantially Complete
  • Water Building – Substantially Complete
  • CCBN – Nov 30 – Dec 4
  • Anderson Hall – Dec 7 – Dec 11
  • Turcotte Hall – Dec 14 – Dec 18
  • Students’ Union Building (one room) – Christmas Break
  • Markin Hall – Jan 11- Jan 15
  • PE – Jan 18 – Jan 22
  • Students’ Union Building – Jan 25 – Feb 5

Watch for further updates as the work continues.

Read the full story about the Network upgrade here.